BMC Plans ₹46 Crore Repairs and Noise Barriers on Jogeshwari, Goregaon Flyovers
The BMC has invited bids for nearly ₹46.05 crore in repairs and upgrades to the Jogeshwari road overbridge and MTNL flyover in Goregaon. The project includes structural repairs, bearing replacement, expansion-joint work, crash barriers and noise barriers.

Key Takeaways
- Strategic developments align with India's long-term infrastructure and technology trajectory.
- Institutional market observers point to sustained corporate expansion and regulatory certainty.
The Brihanmumbai Municipal Corporation (BMC) has floated a tender worth nearly ₹46.05 crore for major repairs and safety upgrades to the existing Jogeshwari road overbridge (ROB) and the MTNL flyover in Goregaon.
The estimated project cost is ₹46.04 crore, excluding GST. Contractors participating in the tender will be required to submit an earnest money deposit of ₹46.05 lakh.
Structural repairs planned for two flyovers
The BMC project covers more than routine road resurfacing. It includes repairs to several structural components of both bridges.
The proposed work includes polymer treatment of structural members, anti-corrosive painting of structural steel, epoxy grouting for bridge abutments, piers and prestressed concrete (PSC) girders, as well as epoxy painting.
The civic body has also included repairs to steel staircases, construction of reinforced cement concrete (RCC) parapets and sections of medians.
Other works listed in the tender include lifting and replacing bridge bearings, repairing expansion joints, asphalt milling, structural steel repairs and installation of crash barriers.
Noise barriers included in BMC project
The project also provides for noise barriers on the two structures. Both flyovers are situated along busy traffic corridors in densely populated areas of Mumbai's western suburbs, where residential and commercial developments are located close to major roads.
However, the tender does not provide details on the proposed height, material or design of the noise barriers.
The BMC has also made traffic management a key condition of the project because construction will take place while vehicles continue to use the roads.
Contractors will be required to install barricades, blinkers, warning boards, diversion signage and lighting in coordination with traffic authorities. The tender also requires warning boards carrying the message "Go slow, work in progress" at both ends of work zones.
Barricading will have to prevent pedestrians and vehicles from entering areas where construction equipment is operating.
Contractors responsible for utility and property protection
The tender places responsibility on contractors for protecting existing utilities and structures during excavation and demolition.
Any damage caused to existing properties or utility infrastructure, including expenses related to compensation or reconstruction, will have to be borne by the contractor.
To maintain construction continuity, the BMC has permitted work on Saturdays, Sundays, public holidays and during night hours.
Contractors will have to deploy dedicated workers and the required equipment for the project. The civic body has warned that failure to maintain continuity of work could lead to penalties.
The project is expected to address structural maintenance and traffic safety requirements on two important flyovers while also introducing noise barriers along these heavily used western suburban corridors.
Mumbai Weekly Staff
Editorial correspondent reporting on national and global stories for Mumbai Weekly.
More In India
View All India →
Prof. Dr. Arjun Chavan: A Scholarly Career Rooted in Hindi Literature and Research
After 38 years as a Professor and Head of the Hindi Department at Shivaji University, Kolhapur, Maharashtra, Prof. (Dr.) Arjun Chavan continues his literary work as an independent scholar and author. His career has covered Hindi literature, comparative literary studies, translation, research methodology, poetry, editing and academic research.